A Pull planning system halves lead time

Auxiliary company of the automotive sector defines a new value stream model by deploying production levelling mechanisms and using Kanban cards to streamline the information flow.

Reduction of lead time from 21 to 11 days
€2,5M reduction of stock
5% increase in productivity
65% reduction in storage area
Daily planning work delegated to middle management
Contact us

NEEDS

  • To reduce stock levels.
  • To reduce logistic costs.
  • Greater flexibility (in terms of response to changes in demand).

IMPROVEMENT PROCESS

  • Analysing and designing a Lean value stream.
  • Designing a demand forecast model.
  • Production levelling.
  • Radical improvement of external logistics and integration with internal logistics.
  • Kanban for process interface connection.
  • Visualisation of the overall process.
caso exito

Related methodologies

See methodologies

Lean Manufacturing

Adjustment to demand using minimum resources and continuously eliminating waste.
See more
caso exito

Related methodologies

See methodologies

Extended value stream

Integration of supply, distribution and manufacturing activities in an efficient overall value stream.
See more

Cookie alert

This website uses own and third party cookies to optimize your browsing, adapt to your preferences and perform analytical tasks. By continuing to browse you accept our cookie policy.

Accept